Zambia tells Parliament its power line to Tanzania will be ready by mid-2029
The 2,300 km link would join the power pools of southern and eastern Africa and let Zambia trade up to 500 MW. Chinese contractors have started surveys on the first stretch.

In 30 seconds
- Zambia's energy minister, Peter Kapala, told Parliament on 5 November that the Zambia to Tanzania power line should be commissioned by the second quarter of 2029.
- The whole corridor is about 2,300 km and is estimated at $1.2 billion. Zambia's part is 613 km.
- Zambia has $292 million in grants for its section, from the World Bank, the EU and the UK.
- The link would let Zambia trade up to 500 MW and join the Southern and Eastern Africa power pools.
A power line first agreed more than a decade ago now has a finish date. In a ministerial statement to Zambia's Parliament on Thursday, 5 November, the minister responsible for energy, Peter Kapala, said the line linking Zambia to Tanzania "is therefore scheduled to be commissioned by the second quarter of 2029", Reuters reported.
What is being built
The full corridor runs about 2,300 km and is estimated to cost $1.2 billion, Zambia Monitor and Reuters reported. Zambia, Tanzania and Kenya signed an agreement for it in December 2014.
Zambia's own section is 613 km, from Pensulo substation in Serenje District to Nakonde, near the Tanzanian border, through Mpika and Kasama, Zambia Monitor reported. Kapala said the full work in Zambia should take 24 months.
The line would join the Southern African Power Pool with the Eastern Africa Power Pool. Kapala said it "will enable Zambia to trade up to 500 megawatts of power", Zambia Monitor reported.
Who is paying, who is building
Zambia's section is paid for by $292 million in grants: $245 million from the World Bank's IDA, $30 million from the European Union and $17 million from the United Kingdom, according to Zambia Monitor and Ecofin Agency. The state power company, ZESCO, is running the procurement in five packages.
The first two contracts, for about 386 km of lines from Pensulo to Mpika and Mpika to Kasama, went to a Chinese group in October. Reuters calls it Sinotech Consortium; Ecofin spells it Sinotec. Ecofin says the contractor began site surveys on 2 November, and that the contracts for the Kasama to Nakonde stretch should be awarded by March 2027.
News Diggers reported that Kapala said construction would begin in 2027, and that he promised no load shedding in Zambia despite an expected El Niño. We could read only the opening of that report, so treat the load shedding pledge with care.
Why it matters for Nigeria
West Africa is building its own links. The WAPP North Core line, joining Nigeria to Niger, Benin, Togo and Burkina Faso, is more than 75 per cent built, TCN said last week. Read that story. Zambia's case shows how long these lines take: twelve years from agreement to a target date, and grants from three donors to pay for one country's share.
What it means for you
Lines like these let a country with spare power sell it to a neighbour that is short, instead of letting it go to waste. For Nigerians, the regional line that matters is WAPP North Core. When it is done, power will be able to move more freely between Nigeria and its neighbours. Whether that helps your light at home depends on Nigeria first making enough power for itself.
Words to know
- Power pool
- A group of neighbouring countries whose grids are linked so they can buy and sell electricity. West Africa has its own, WAPP.
- Interconnector
- A high-voltage line that links the grids of two countries.
- kV
- Kilovolt, a measure of how high the voltage on a line is. Bigger lines carry more power over longer distances.
Sources
- Zambia Monitor: Zambia-Tanzania power interconnector to be commissioned by 2029, Parliament told (5 Nov 2026)
- Reuters via Club of Mozambique: Zambia expects power line to Tanzania to be operational in 2029 (5 Nov 2026)
- Ecofin Agency: Zambia awards first contracts for 500MW Tanzania power interconnector (6 Nov 2026)
- SolarQuarter: Zambia to Tanzania 2,300 km power interconnector targeted for commissioning by 2029 (6 Nov 2026)
- News Diggers: With or without El Niño, there'll be no load shedding, Kapala (6 Nov 2026)
Spotted an error? Tell us and we will fix it and say so.