Namibia's port and railway companies object to parts of Dangote's Walvis Bay fuel terminal plan

The port authority rejected the first pipeline route and the state railway wants fuel moved by train, not tanker, according to a draft environmental assessment. Dangote's team has agreed to use the port's pipeline corridor. Building cannot start until an environmental permit is granted.

The Dangote Group logo
Logo: Dangote Group

In 30 seconds

  • Namport, which runs Namibia's ports, objected to the planned pipeline route inside Walvis Bay's North Port, saying it ran too close to homes, New Era reports.
  • TransNamib, the state railway, asked in writing for rail to be the main way fuel leaves the terminal. The draft assessment says road alone would mean about 270 tankers a day.
  • Dangote's team confirmed on 10 November that pipelines inside the port will follow Namport's official corridors.
  • The N$43 billion (about $2.6 billion) terminal still needs an environmental clearance certificate before construction can start.

The fuel terminal Aliko Dangote launched in Namibia this month has run into objections from two state companies. Both are set out in a draft environmental impact assessment for the project, seen by Namibia's state-owned New Era newspaper and reported on 19 November. Billionaires.Africa reported the same details on Sunday.

The terminal, at Farm 58 in Walvis Bay, would store fuel from Dangote's 650,000-barrel-a-day refinery in Lagos. New Era puts its cost at N$43 billion. Billionaires.Africa converts that to about $2.6 billion. When Dangote broke ground on 4 November the figure given was $2.5 billion, as we reported then.

The port's objection

Fuel would come ashore at Namport's existing oil jetty and travel by pipeline to the terminal. Namport objected to the first route through the North Port. It said the layout was flawed, came too close to homes and clashed with the port's long-term plan, New Era reports. It also turned down an alternative route over high sand dunes.

Namport's chief executive, Andrew Kanime, confirmed the objection to New Era. He said the port wants one shared corridor for compatible pipelines, including fuel, LNG, LPG and green hydrogen, kept away from homes so that any burst happens "in the middle of an industrial area".

The railway's request

TransNamib asked in writing for rail to be the main way fuel leaves the terminal. "Moving fuel by road poses a severe safety hazard," it said, according to both outlets. It asked for urgent talks.

The draft assessment gives the numbers. If all fuel went by road, about 270 tankers a day would leave the site, some 540 heavy vehicle movements. The design includes a rail gantry with 10 loading points and a siding of about 600 metres. One train a day would replace about 55 tankers, cutting road traffic to about 215 tankers a day.

Dangote's answer

On 10 November Dangote's team confirmed that all pipelines inside the port will follow Namport's official corridors, New Era reports. The draft assessment says no fuel pipeline will run along the port's southern edge. Outside the port, lines will follow the town's shared corridor. The final route still needs Namport's formal approval and a servitude agreement with the municipality.

Still waiting for a permit

Construction cannot start until Namibia's Environmental Commissioner rules on the project, both outlets say. Billionaires.Africa reports that the environment ministry said last week it had not yet received the clearance application. Walvis Bay's mayor had not answered New Era's questions by the time it went to print.

What it means for you

This does not affect fuel supply or prices in Nigeria. It matters because the terminal is Dangote's first big step to sell Lagos-refined fuel into southern Africa, including a planned pipeline to Botswana, Zambia and Zimbabwe, according to Billionaires.Africa. Exports bring dollars into Nigeria. How fast Namibia clears the project will show how quickly that market opens.

Words to know

EIA
Environmental impact assessment, a study of how a project would affect people and nature. In Namibia a project needs clearance from the Environmental Commissioner before work starts.
Servitude
A legal right to run a pipe or cable across land owned by someone else, here the town.

Sources

  1. New Era: Dangote's N$43b fuel project faces regulatory pushback as Namport, TransNamib raise objections (19 Nov 2026)
  2. Billionaires.Africa: Dangote's $2.6 billion Namibia fuel hub faces port, rail objections (22 Nov 2026)

Spotted an error? Tell us and we will fix it and say so.