New drilling at the Agbami deepwater field slips back to 2027, a partner's results show, and its Nigerian output is down by nearly a fifth
Meren Energy, which holds stakes in Agbami, Akpo and Egina, now expects the rig for Agbami and the nearby Ikija prospect in the first quarter of 2027. In May it had pulled the work forward to late 2026. It has cut its 2026 spending plan twice.

In 30 seconds
- Meren Energy's third-quarter results, released on 10 November, say the rig for Agbami and Ikija is "now expected to arrive in Q1 2027".
- In August Meren said the Ikija well was on schedule to start in the fourth quarter of 2026. In May it had moved the work forward from 2027.
- Meren cut its 2026 spending plan to $70 million to $90 million, from $100 million to $140 million at the start of the year, because some drilling moves into 2027.
- Its working-interest output fell to 25,300 barrels of oil equivalent a day in the third quarter, from 31,100 a year earlier, about 19 per cent less.
New wells at Agbami, a deepwater oil field off Nigeria, will now wait until 2027. The change is in the third-quarter results of Meren Energy, a partner in the field, released on 10 November.
Meren holds working interests in the Agbami, Akpo and Egina fields, its release says.
The rig moves back again
Meren said the drilling rig for Agbami and the nearby Ikija prospect is "now expected to arrive in Q1 2027". The plan is three infill wells at Agbami and one appraisal well at Ikija.
This is a reversal. In May, BusinessDay reported that Meren had brought the work forward by about six months, from early 2027 to late 2026. In its August results Meren said the Ikija well was "on schedule to commence in Q4 2026".
The November release says only that the plan was revised "following optimisation".
Spending cut twice
Meren started 2026 planning to spend $100 million to $140 million. In August it cut that to $90 million to $120 million, saying drilling costs had moved into 2027. Its new figure is $70 million to $90 million, because "some drilling activities are deferred into 2027".
Output down
Meren's working-interest output was 25,300 barrels of oil equivalent a day in the third quarter, against 31,100 a year earlier. That is a fall of about 19 per cent. The release gives no reason for the fall. Meren now expects 25,000 to 27,000 barrels of oil equivalent a day for the full year, on a working-interest basis.
It raised its forecast for EBITDAX, earnings before interest, tax, depreciation and exploration costs, to $390 million to $440 million. It will pay its fourth dividend of the year, about $25.1 million.
Akpo goes ahead
At Akpo, the news is better. The rig is in place and the operator "is preparing to commence drilling in November 2026", the release says. The first well will test a prospect called Akpo Far East. We reported on the Akpo drillship on 7 November.
Meren also points to the Deep Offshore Incentives Order signed in August, which gives tax credits to deepwater projects that reach a final investment decision by the end of 2029.
What it means for you
Deepwater fields like Agbami are a large part of what Nigeria produces and exports. Older fields lose output every year unless new wells are drilled. A delay of a few months means Agbami's decline runs longer before new wells help. Meren's release does not say why it moved.
Words to know
- Infill well
- A new well drilled between existing wells in a producing field to reach oil the first wells miss.
- Appraisal well
- A well drilled after a discovery to find out how big it is and whether it is worth developing.
- Working interest
- A company's share of a field's output, before deductions under its contract with the government.
- Capex
- Capital spending, money spent on drilling, equipment and other long-term work.
Sources
- Meren Energy: Third quarter 2026 results and fourth dividend distribution (10 Nov 2026, Cision/Newswire)
- Meren Energy: Second quarter 2026 results (11 Aug 2026, via Inderes)
- BusinessDay: Canada's Meren pulls forward Nigeria drilling as deepwater output slumps (19 May 2026)
Spotted an error? Tell us and we will fix it and say so.