Power returns to Lagos after a damaged line is repaired, as DisCos apologise and ask the minister to take charge
The minister says supply to Lagos is back above 1,000 MW after the Benin-Egbin line was fixed. A second Lagos line, out for about 18 months, is promised by the end of November.
In 30 seconds
- Minister of Power Joseph Tegbe said on Monday that the damaged Benin-Egbin 330kV line is repaired and supply to Lagos is back above 1,000 MW.
- He said supply had returned largely in Lagos, Ogun, Oyo, Kwara and the FCT, with work going on in the remaining areas.
- The Osogbo-Ikeja West line, out for about 18 months, could add 400 MW to Lagos. TCN has promised to finish it by the end of November.
- The DisCos' association apologised to Nigerians and said the minister "needs to take charge" of the blame game over gas.
After more than a week of poor supply in Lagos, Abuja and several other states, the Federal Government says the worst is over for Lagos.
What the minister said
In an update shared on social media on Monday, Minister of Power Joseph Tegbe said the Benin-Egbin 330kV transmission line, which had been vandalised, was repaired and back in service. Supply to the Lagos Complex, the group of substations that feeds the state, had risen above 1,000 MW, he said, "effectively normalising to the condition before the disruption", Daily Champion reported.
He said supply had returned largely in Lagos, Ogun, Oyo, Kwara and the FCT. Some headlines called these six states; the update as reported names five states and the FCT.
"Our teams continue to work to restore full supply to the remaining affected locations," Tegbe said, Tribune reported. He did not say which areas were still affected.
He also spoke on a live TVC programme on Monday, WorldStage reported, saying the government had resolved the problems of the past few days.
Why Lagos lost so much
Tegbe said planned maintenance at Egbin Power Station, together with the outage on the Benin-Egbin line, cut almost 800 MW from the Lagos system. The Benin-Egbin line normally carries between 300 MW and 400 MW into Lagos, he said.
Lagos has four major transmission lines, and only three work, he said. The fourth, the Osogbo-Ikeja West 330kV line, has been out of service for about 18 months after about six towers in a swampy area were vandalised. Tegbe said it could add 400 MW to Lagos and that the Transmission Company of Nigeria (TCN) had promised to finish restoring it by the end of November.
On Friday, the minister had promised the first units back "within the next 48 to 72 hours". Our report on that promise. His update did not say whether all the Egbin units are back, or how much the whole grid is now producing.
DisCos apologise, and ask for one story
Sunday Oduntan, who heads the Association of Nigerian Electricity Distributors (ANED), apologised to Nigerians on Channels Television's Sunrise Daily on Monday, Nairametrics reported. "I'd like to first of all start by apologising to Nigerians," he said.
He criticised the different explanations given by NISO, the grid operator, and NNPC over gas supply. NISO said on 5 November that low gas and low water at the dams were behind the drop. NNPC said on 7 November that its gas pipelines had no constraints. "I think the Minister of Power needs to take charge," Oduntan said.
The gas question is still open. None of the statements we have read gives figures for gas delivered to each power plant. Daily Trust reported that the Association of Power Generation Companies says the government owes its members about ₦6.8 trillion and that gas suppliers are owed about ₦3.3 trillion. We have not seen those figures from the government.
What it means for you
If you are in Lagos, Ogun, Oyo, Kwara or Abuja, supply should be close to what it was before the trouble began. If your feeder is still dark or on very short hours, report it to your DisCo with your feeder name, because the national problem is no longer a good reason. Lagos is still one line short. If TCN keeps its end of November promise on the Osogbo-Ikeja West line, the state gets a spare route, so the next damaged line should hurt less. Why one broken line can darken Lagos, simply.
Words to know
- 330kV line
- One of the high-voltage lines that carry large amounts of power across the country, from power stations to big substations.
- Lagos Complex
- The group of transmission substations that feed Lagos. Power for most of the state passes through it.
- Load shedding
- Switching feeders off in turns when there is not enough power for everyone.
Sources
- Tribune: FG restores power supply to six states after vandalism (Nov 2026)
- Daily Champion: Tegbe claims restoration of power to Lagos, Ogun, 4 other states after vandalisation (10 Nov 2026)
- WorldStage: Power Minister confirms resumption of electricity supply to states in darkness for days (9 Nov 2026)
- Nairametrics: DisCos ask power minister to address blame game amid nationwide electricity shortages (9 Nov 2026)
- Daily Trust via AllAfrica: Blackout persists as NNPC, NISO trade blame (9 Nov 2026)
Spotted an error? Tell us and we will fix it and say so.